NEW QUESTION # 127
In which process should the specified quality methods he used to/prove that a product meets its quality criteria?

  • A. Managing product delivery
  • B. controlling a stage
  • C. Managing a stage boundary
  • D. closing a project

Answer: A

Explanation:
The 'Managing Product Delivery' process in PRINCE2 is where the specified quality methods are applied to ensure that a product meets its quality criteria. This process focuses on the acceptance, execution, and delivery of the project's products, ensuring that they are produced to the defined quality standards as part of the overall project delivery.References: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation


NEW QUESTION # 128
Which is a purpose of an End Stage Report?

  • A. Summarize progress to enable the Project Board to decide what action to take next
  • B. Provide a plan for the next stage of the project
  • C. Provide the detailed analysis of a deviation and offer options for the way to proceed
  • D. Summarize how the project performed against the version of the Project Initiation Documentation used to authorize it

Answer: A


NEW QUESTION # 129
How does the 'managing product delivery' process ensure that the team manager's perspective is provided in a work package?

  • A. the work packages provided by the project manager are agreed by the team manager
  • B. The work packages are defined by the team manager and supported by a team plan
  • C. The stage plan covering the work packages is created with input from the team manager
  • D. The team plans are checked by project assurance against the work packages

Answer: A


NEW QUESTION # 130
Which characteristic distinguishes a project from regular business operations?

  • A. Produces benefits
  • B. Introduces business change
  • C. Manages stakeholders
  • D. Incurs cost

Answer: B


NEW QUESTION # 131
Which plan provides the Business Case with costs during the Initiating a Project process?

  • A. Initiation Stage Plan
  • B. Project Plan
  • C. Stage Plan
  • D. Team Plan

Answer: B

Explanation:
During the Initiating a Project process in PRINCE2, the Project Plan provides the Business Case with necessary details, including cost estimates. This plan outlines the overall scope and timing of the project and sets the baseline for project management activities, including cost control. References: PRINCE2 Foundation manual, PRINCE2 official resources


NEW QUESTION # 132
Which control must be used as a minimum requirement for applying the 'progress' theme?

  • A. Highlight reports
  • B. Tolerances
  • C. A project plan
  • D. An Issue register

Answer: B

Explanation:
Tolerances are a minimum requirement for applying the 'progress' theme in PRINCE2. They define the allowable deviations in time, cost, quality, scope, risk, and benefit objectives that do not require escalation to higher management levels. This control mechanism ensures that the project operates within agreed boundaries without frequent upper management intervention.References: = PRINCE2 7 Foundation handbook and online resources


NEW QUESTION # 133
Which is a purpose of the Starting up a Project process?

  • A. Prevent poorly conceived projects from ever being initiated
  • B. Learn lessons from this project
  • C. Document how changes required by corporate or programme management will be reviewed
  • D. Ensure the communication requirements of all stakeholders are documented

Answer: A


NEW QUESTION # 134
According to the guidance for effective quality management, when should the requirements for a product be captured?

  • A. When the project team needs to test the product
  • B. When the project team needs to know how the product will be delivered
  • C. When the project team realizes that the product is needed
  • D. When the project team needs to know whether the product has been approved

Answer: C

Explanation:
In PRINCE2, the requirements for a product should be captured early in the process, specifically when the project team realizes the need for that product. This approach ensures that the project delivers what is actually required and expected. Capturing requirements early helps in detailed planning and allows for effective quality management throughout the product's development and delivery phases.References: (PRINCE27 Foundation Handbook, AXELOS)


NEW QUESTION # 135
According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

  • A. When authorized by the corporate, programme management or the customer
  • B. After the executive has been appointed
  • C. Before work to start the project commences
  • D. When an organization produces its business plans

Answer: C

Explanation:
According to the 'continued business justification' principle in PRINCE2, a justifiable reason for a project is required before any work to start the project begins. This ensures that projects are initiated only when there is a clear business need, aligned with organizational objectives, and there is an expectation of value creation.
The business case is developed during the initial stages of the project and is maintained and reviewed throughout the project lifecycle.
PRINCE2 Foundation Manual


NEW QUESTION # 136
Which product is created in the 'starting up a project' process to define and confirm the scope of the project?

  • A. Project brief
  • B. Project mandate
  • C. Initiation stage plan
  • D. Project initiation documentation

Answer: A

Explanation:
Section: Volume B


NEW QUESTION # 137
Which process monitors work that has been assigned to a team manager?

  • A. Managing product delivery
  • B. Controlling a stage
  • C. Directing a project
  • D. Managing a stage boundary

Answer: A

Explanation:
Reference https://www.whatisprince2.net/prince2-process-managing-product-delivery.php


NEW QUESTION # 138
Which is a purpose of a Project Brief?

  • A. Describe the reporting requirements of the various layers of management involved with the project
  • B. Enable the assembly of the project mandate
  • C. Provide a solid basis for the initiation of the project
  • D. Describe how changes to products will be controlled

Answer: C

Explanation:
The purpose of a Project Brief in PRINCE2 is to provide a solid basis for the initiation of the project. The Project Brief includes the outline of the project's objectives, scope, constraints, and assumptions. It is developed during the 'Starting up a Project' process and is used to ensure that a clear, concise, and feasible plan is proposed before the project is formally initiated.
PRINCE2 7 Foundation resources and materials.


NEW QUESTION # 139
Which statement about risks is FALSE?

  • A. A risk that could have a negative impact on a project's objectives is known as a threat
  • B. A risk is an uncertain event that, should it occur, will have an effect on a project's objectives
  • C. A risk that could have a positive impact on a project's objectives is known as an opportunity
  • D. A risk that a project's product is incomplete is known as an off-specification

Answer: D


NEW QUESTION # 140
What theme establishes the mechanisms to judge whether a project is worthwhile investing in?

  • A. Risk
  • B. Quality
  • C. Business Case
  • D. Plans

Answer: C


NEW QUESTION # 141
Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?

  • A. Processes
  • B. Themes
  • C. Tailoring PRINCE2 to the project environment
  • D. Principles

Answer: D


NEW QUESTION # 142
Which product identifies the management stages and timescales of a project?

  • A. Initiation Stage Plan
  • B. Project Plan
  • C. Project Brief
  • D. Project Product Description

Answer: B


NEW QUESTION # 143
Which is a purpose of a Project Brief?

  • A. Define the quality techniques and standards to be applied during the project
  • B. Ensure that there is a common understanding of the starting point for the project
  • C. Confirm that the Project Plan is able to deliver the Business Case
  • D. Capture lessons from previous projects

Answer: B


NEW QUESTION # 144
According to the 'continued business justification' principle, what must project benefits be aligned to?

  • A. The direction of the project board
  • B. Regular deliveries throughout the project
  • C. The technology available
  • D. The business objectives

Answer: D

Explanation:
Explanation/Reference:
Reference https://www.whatisprince2.net/prince2-principle-continued-business-justification.php


NEW QUESTION # 145
Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?

  • A. End Project Report
  • B. Checkpoint Report
  • C. Product Status Account
  • D. End Stage Report

Answer: D


NEW QUESTION # 146
What is the change authority role permitted to authorize?

  • A. Changes to the project that do not exceed a defined budget
  • B. Risks to the project
  • C. Adjustments to the limits on the change budget
  • D. Changes to stage tolerance

Answer: A

Explanation:
Section: Volume B


NEW QUESTION # 147
What is a supplier of a PRINCE2 project responsible for?

  • A. Establishing the project's governance
  • B. Providing resources to deliver the project outputs
  • C. Providing the project mandate
  • D. Realizing the benefits from the project

Answer: B

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wikidot.com/senior-supplier


NEW QUESTION # 148
Which term is defined as the means by which an organization transitions to a desired future state?

  • A. Change management
  • B. Communication management
  • C. Risk management
  • D. Issue management

Answer: A

Explanation:
Change management' is defined as the means by which an organization transitions to a desired future state. It involves the processes and techniques used to manage the people side of change to achieve the required business outcome, ensuring that changes are implemented smoothly and effectively.References: PRINCE27 Foundation materials on project management terms and definitions.


NEW QUESTION # 149
Identify the missing words in the following sentence.
A benefit of adopting PRINCE2 is that it can be applied to [ ? ] - and can easily be implemented alongside specialist techniques.

  • A. all types of programmes
  • B. programmes and projects
  • C. any type of project
  • D. business as usual

Answer: C


NEW QUESTION # 150
Which is a purpose of a Project Product Description?

  • A. Provides a list of all the products to be delivered by the project
  • B. Records the costs and timescales for delivery of the project's final product
  • C. Defines what the project must deliver in order to gain acceptance
  • D. Shows the dependencies between the project's products to aid planning

Answer: C


NEW QUESTION # 151
The project board is reviewing the project initiation documentation (PID) to decide whether the project should continue or close. What should the project board ensure the PID is aligned with?

  • A. The business' existing governance practices
  • B. The project's delivery method
  • C. The ways of working used on previous projects
  • D. The business objectives

Answer: D

Explanation:
hen the project board reviews the Project Initiation Documentation (PID), it is essential to ensure that the PID is aligned with the business objectives. The PID should encapsulate the project's definition, including the reasons for undertaking the project, the benefits expected, and how it aligns with the broader business goals.
Ensuring this alignment helps validate that the project remains viable and worthwhile as it progresses.
References: (PRINCE27 Foundation Handbook, AXELOS)


NEW QUESTION # 152
......

Last PR2F practice test reviews: Practice Test EXIN dumps: https://prepaway.testkingpass.com/PR2F-testking-dumps.html