Upon successfully passing the C-TS422-2021 certification exam, candidates will be recognized as SAP Certified Application Associates in SAP S/4HANA Production Planning and Manufacturing 2021. SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing 2021 certification demonstrates that the individual has the skills and knowledge required to effectively implement and support SAP's production planning and manufacturing solutions, and can be a valuable asset to any organization looking to optimize their manufacturing processes with SAP technology.
SAP C_TS422_2021 is a certification exam that focuses on Production Planning and Manufacturing in SAP S/4HANA. SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing 2021 certification is designed to validate the candidate's skills and expertise in implementing and configuring SAP S/4HANA Production Planning and Manufacturing solutions. The SAP C_TS422_2021 exam is intended for application associates who have experience in implementing and customizing production planning and manufacturing functionality in SAP S/4HANA.
NEW QUESTION # 48
You want to insert an operatio at a certain time on work center. The planning direction is forward. The disired dispatching time concides with an operation that has previously been dispatched. How does the insertion take place?
- A. The previously dispatched operation stays as is; the new operation is inserted before the the dispatched operation.
- B. The new operation is inserted at the desired time; the previously dispatched operation is moved forward.
- C. The previously dispatched operation stays as is; the new operation is inserted after the the dispatched operation.
- D. The new operation is inserted at the desired time; the previously dispatched operation is moved backward.
Answer: D
NEW QUESTION # 49
How can you set up the supply source for the Kanban process in SAP S/4HANA?
- A. Using stock transfer reservations for stock transfer
- B. Using purchasing costs for automated source prioritization
- C. Using quotations for internal and external procurement
- D. Using run schedule quantities for in-house production
- E. Using purchase orders for external procurement
Answer: A,D,E
NEW QUESTION # 50
Which actions does the system preform by default when you save a confirmation for a finished product in repetitive manufacturing?
- A. Material staging for nex order in sequence
- B. Posting of goods receipt for the product
- C. Archiving of documents for assembly scrap
- D. Reduction of associated capacity requirements
- E. Posting of production costs to the production cost collector
Answer: B,D,E
NEW QUESTION # 51
Your client is asking for your advice on material master numbering in SAP S/4HANA. What do you need to consider?
- A. The number of leading zeros for internal numbers is client-specific.
- B. The maximum mater all number length is 40 for external numbers and 18 for internal numbers
- C. The display template for material numbers applies to all clients.
- D. In Customizing you can decide by material type whether to use the long material number.
Answer: B,C
NEW QUESTION # 52
How can you carry out cost object controlling for production orders?
- A. Product-related
- B. Order-related
- C. Milestone-related
- D. Cost-related
Answer: A,B
NEW QUESTION # 53
Where do you maintain data to determine the duration of an operation for production?
- A. Bill of material (BOM)
- B. Routing
- C. Work center
- D. Material master
Answer: B,C
NEW QUESTION # 54
What is a work center hierarchy in planning in SAP S/4HANA?
- A. A group of work centers in a parallel sequence that is used to split production quantities and work on them in parallel
- B. A group of alternative work centers for production, structured in hierarchy levels by priorities
- C. A group of alternative work centers providing a cumulative available capacity for production.
- D. A group of work centers in a production line being used in sequence for production
Answer: C
NEW QUESTION # 55
Which of the following is valid sequence of the main activities in production order processing?
- A. Creation, release, settlement, goods issue, confirmation, goods receipt
- B. Creation, release, printing, goods issue, confirmation, goods receipt
- C. Creation, availability check, release, material widrawal, confirmation
- D. Creation, printing, release, goods issue, confirmation, goods receipt
Answer: B,C
NEW QUESTION # 56
How can you limit the validity of a bill of material (BOM)?
- A. By material type
- B. By plant
- C. By industry
- D. By period
Answer: B,D
NEW QUESTION # 57
What detremines whatherthe planned independent requirements in MRP are consumed by other requrements?
- A. Requirements type
- B. Consumption sequence procedure
- C. Order type
- D. Requirements profile
Answer: A
NEW QUESTION # 58
You want to create a production order from a planned order. What methods could you use?
- A. Partial conversion
- B. Collective conversion
- C. Order release
- D. Combined conversion
Answer: A,B
NEW QUESTION # 59
You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
- A. Production order release
- B. Kanban
- C. Material requirements planning
- D. Backflushing
Answer: C
NEW QUESTION # 60
Which master data object governs the relationship between supply source and demand source in the Kanban process?
- A. Production supply area
- B. Replenishment strategy
- C. Control cycle
- D. Rate routing
Answer: C
NEW QUESTION # 61
Which information is required when you created a production master in SAP S/4HANA?
- A. Product type
- B. Base unit of measure
- C. Industry sector
- D. Selective screen for views
Answer: A,D
NEW QUESTION # 62
What does it mean for the production planner when MRP works with infinite capacities?
- A. MRP assigns capacity requirements automatically after the last scheduled order on a work center.
- B. MRP creates capacity requirements without checking the capacity of a work center.
- C. MRP creates capacity requirements only if the work center has sufficient capacity.
- D. MRP assigns capacity requirements automatically to work center is with the earliest available capacity.
Answer: B
NEW QUESTION # 63
Your company produces a finished good based on a forecast and expects it to being stock when customers order it. If customers order more than the forecasted quantity, the production quantity should be increased to try to meet the extra demand. Which planning strategy do you use?
- A. Make-to-stock production (10)
- B. Make-to-order production (20)
- C. Planning with final assembly (40)
- D. Planning without final assembly (50)
Answer: C
NEW QUESTION # 64
You use planning strategy Finite Scheduling - with Reverse adn want to allow scheduling in the past. How can you achive this?
- A. Specify a positive offset time in the strategy profile.
- B. Specify a negative lanning horizon in the strategy profile.
- C. Specify a positive planning horizon in the strategy profile.
- D. Specify a negative offset time in the strategy profile.
Answer: D